Construction Progress - Part III

Construction continues for the new MSU Surplus Store and Recycling Facility. Last time we visited the site were were able to see the process of placing the footings for the facility. This work is continuing for now with 50+ aggregate piers being installed per day. Overall there will be approximately 888 of these footings installed for the building. The newest part of the project is the start of the installation of the Storm Sewer Drains on the west side of the facility. This will be followed by sanitary, water main, then electric duct bank.

Rember to keep checking back for more photos and updates on the progress of construction.