Thursday, February 12, 2009

Construction Progress - Part XVI

While there may not be many major updates to the new MSU Surplus Store and Recycling Center there has certainly still been quite a bit of progress made through out the facility. 90% of the interior wall panels have been finished in the MSU Surplus Store side of the facility and work has begun in the Recycling side. Much of interior electrical conduit has been run including the instillation of electrical panels in the mezzanine area. All of the exterior overhead doors have now been installed and the translucent panels have also been completed. The largest change now is the completion of concrete floors in the MSU Surplus Store processing area and the sales floor and storage area should be done very soon.