We are getting closer and closer to the completion of the new MSU Surplus Store and Recycling Center. We are expecting to move to the new building in two months from now. Work is still continuing both inside and outside as sidewalks and parking lots are being paved.The ceilings are installed and electrical wires are being run.
The most exciting new feature is a large block S located by the MSU Surplus Store main entrance. It will be visible from Green Way (our new road) to make it easy to locate our main entrance.
Inside most of the large MSU Recycling equipment is installed, including the sort line and baler . The rain water retention bins that store gray water for use in the building are installed, including much of the pipes to collect and move this water.